Under-Construction Penalty Clauses

Under-construction penalty clauses specify financial consequences for developer delays, requiring compensation to buyers for late completion beyond agreed handover dates.

Penalty StructureDubai Standard
Delay calculationDays past contractual handover date
Penalty rateAED 10 per square meter per day typical
Maximum capOften 10% of purchase price
Trigger dateAfter grace period (30 to 90 days common)
Automatic applicationShould be automatic, often requires claim
Force majeure exceptionDeveloper not liable for acts of God
Example Calculation1,000 sq ft Unit
Contractual handoverJune 1, 2024
Actual handoverDecember 1, 2024 (6 months late)
Delay days183 days (6 months)
Unit size1,000 sq ft (93 sq m)
Daily penaltyAED 930 (93 sq m times AED 10)
Total penaltyAED 170,190 (183 days times AED 930)
Buyer actionClaim through RERA or deduct from final payment