Project cost encompasses all expenses required to complete property development from land acquisition through construction to final handover, forming the basis for construction loan sizing and developer equity requirements.
| Cost Categories | Components |
| Land acquisition | Plot purchase price |
| Hard costs | Physical construction 60-70% |
| Soft costs | Professional fees, permits 10-15% |
| Financing costs | Interest during construction 8-12% |
| Contingency | Risk buffer 5-10% |
| Detailed Cost Breakdown | Example Villa Development |
| Land | AED 5,000,000 |
| Construction | AED 8,000,000 |
| Architecture and design | AED 400,000 |
| Legal and regulatory | AED 300,000 |
| Marketing | AED 200,000 |
| Financing interest | AED 900,000 |
| Contingency | AED 700,000 |
| Total project cost | AED 15,500,000 |
| Financing Implications | Impact |
| Construction loan 65% LTC | AED 10,075,000 |
| Developer equity required | AED 5,425,000 (35%) |